JAKS - Power operations may support earnings moving forward -

Author:   |    Publish date:


The Hai Duong Vietnam EPC Contract Has Been Progressing Well and the Power Plant Is Reaching the Completion Stage (2Q19: C.82% Vs. 1Q19: 70%) and Likely to be Commencing by Mid-2020. Although Its Construction Orderbook Is Declining and the Property Segment Is Slowing Down, Should the Hai Duong Vietnam Power Start Operation by 2H2020, It Should be Able to Support Its Earnings Moving Forward. Technically, JAKS Could Poise for a Symmetrical Triangle Breakout, Targeting RM1.43-1.50, With a LT TP of RM1.65, While Support Is Located Around RM1.21-1.23, With a Cut Loss Set Around RM1.15.

Power plant is approaching completion. As of 2Q19, its Vietnam EPC contract has been progressing well and it has hit c.82% project completion (vs. 70% in 1Q19. Hence, we believe remaining works will be done in 2020 and the power plant may start commencement by mid-2020.

Declining orderbook and sluggish property segment. However, its orderbook has declined to RM847m in 2Q19 as compared to RM1.07bn a quarter ago. Meanwhile, its property segment could still disappoint given the delay in Pacific Star Tower with completion of the remaining 3 blocks being pushed to 1H2020.

Rising power segment. Nevertheless, should the Hai Duong Vietnam power plant start its operation by 2H2020, this may boost JAKS earnings in the long run.

Poise for symmetrical triangle breakout. JAKS has formed a symmetrical triangle formation over the past two months. The technicals have turned positive and our indicator is suggesting a potential exponential breakout in the near term. Should there be a breakout above RM1.30, next target will be located around RM1.43–1.50, with a LT TP envisaged around RM1.65. Support is pegged along RM1.21-1.23, with cut loss set around RM1.15.

 

Source: Hong Leong Investment Bank Research - 15 Jan 2020

Share this
Labels: JAKS

Related Stocks

Chart Stock Name Last Change Volume 
JAKS 1.54 +0.01 (0.65%) 9,132,400 

  Be the first to like this.
 
anticonman Why 2H 2020 not Feb-Mar'20 like Jaks promoters said power plant commence? Meaning more delay?
15/01/2020 12:53 PM
Tiger66 You cannot catch meh, the data update by HLinvest very outdated.

As of 2Q19, its Vietnam EPC contract has been progressing well and it has hit c.82% project completion (vs. 70% in 1Q19. Hence, we believe remaining works will be done in 2020 and the power plant may start commencement by mid-2020.
15/01/2020 1:46 PM


 

420  316  517  739 

ActiveGainersLosers
Top 10 Active Counters
 NameLastChange 
 EDUSPEC 0.03+0.005 
 XOX 0.050.00 
 PWORTH 0.02-0.005 
 XDL 0.17+0.01 
 PWRWELL 0.3750.00 
 PERDANA 0.47-0.01 
 ISTONE 0.24+0.015 
 MTOUCHE 0.175-0.015 
 INNATURE 0.59-0.065 
 HSI-H8T 0.48+0.045 

TOP ARTICLES

1. WORST IS OVER FOR THIS COMPANY !!! RENEWED BUYING INTEREST EMERGES !! Bursa Master
2. TUN DR M STAYING ON AFTER APAC END NOV 2020 & BEYOND VERY GOOD FOR NFCP BULL RUN, Calvin Tan Research THE INVESTMENT APPROACH OF CALVIN TAN
3. Dayang: My advice for the board of directors - Koon Yew Yin Koon Yew Yin's Blog
4. Dayang: Intelligent investors versus ignorant investors - Koon Yew Yin Koon Yew Yin's Blog
5. TOP 10 VALUABLE INVESTMENT SECRETS MY JOHOR SIFU TAUGHT ME(REPOSTING) (Calvin Tan Research) THE INVESTMENT APPROACH OF CALVIN TAN
6. Government Stimulus on 27 Feb : Complete List of Stocks to Watch ! The Pelham Blue Fund
7. Anwar to meet Agong tomorrow, but aide says scheduled ‘long time ago’ save malaysia!!!
8. MYEG and Other Related Stocks to Watch on 24th Feb 2020 Weekly GreenTrades watchlist
Partners & Brokers