ECRL project reaches progress rate of over 60pc

savemalaysia
Publish date: Mon, 25 Mar 2024, 12:35 PM

KOTA BARU, March 25 — The East Coast Rail Link (ECRL) project in Kelantan, Terengganu, Pahang, and Selangor has reached an overall progress rate of 62.40 per cent as of February.

Malaysia Rail Link Sdn Bhd (MRL) chief executive office Datuk Seri Darwis Abdul Razak said to date, the construction work on the ECRL in Kelantan was 75.8 per cent complete.

“The ECRL project in Kelantan covering 43 kilometres involves the construction of two stations, namely a passenger station in Kota Baru and a passenger and cargo station in Pasir Puteh.

“The ECRL line from Kota Baru to the Integrated Transport Terminal (ITT) in Gombak is expected to be completed according to schedule in Dec 2026 and will commence operations in Jan 2027, while the ECRL line from Gombak to Port Klang is expected to be completed by Dec 2027,” he said after attending an iftar event here last night.

Darwis added that the construction of the elevated structure bridges had progressed well in Kelantan.

“Recently, we have achieved three tunnel breakthroughs, bringing the total number of tunnel breakthroughs to 30 out of 41.

“I believe that the construction of the ECRL is on the right track to be completed fully by Dec 2026 for the Kota Baru to Gombak line,” he said.

He said the track laying construction from Kuantan to Dungun along a stretch of 92.2 km had been fully completed.

The 665-kilometre-long ECRL is expected to link Kota Bharu to ITT Gombak in four hours as compared to seven hours by road transport or some 12 hours or more during festive season. — Bernama

 

https://www.malaymail.com/news/malaysia/2024/03/25/ecrl-project-reaches-progress-rate-of-over-60pc/125348