MRT LINE 2 - GUIDEWAY (VIADUCT) | MRT LINE 1 - GUIDEWAY (VIADUCT) | ||
In Sept 2014, MRT reveals findings of investigations on fatal incident in MRT 1. Syarikat Muhibah might not able to get Viaduct for MRT 2. |
Elevated Section V1 |
Syarikat Muhibah & Perniagaan & Pembinaan Sdn Bhd |
|
Package V207 | Mudajaya Corporation Berhad | Elevated Section V3 | Mudajaya Corporation Berhad |
Package V201 | Sunway Construction Sdn Bhd | Elevated Section V4 | Sunway Construction Sdn Bhd |
Package V203 | IJM Construction Sdn Bhd | Elevated Section V5 | IJM Construction Sdn Bhd |
Package V202 | Ahmad Zaki Sdn Bhd | Elevated Section V6 | Ahmad Zaki Sdn Bhd |
Package V208 | MTD Construction Sdn Bhd | Elevated Section V7 | MTD Construction Sdn Bhd |
Package V210 | Malaysian Resources Corporation Berhad | - | - |
Package V204 | WCT Berhad | - | - |
Package V209 | Tender Submission Date 21/11/2016 | Elevated Section V8 | UEM Construction Sdn Bhd |
Package V206 | Tender Submission Date 22/11/2016 | Elevated Section V2 | Gadang Engineering (M) Sdn Bhd |
Package V205 | Tender Submission Date 12/1/2017 |
Package V205, 206 and 209 remain not awarded.
Gadang and UEM likely to gain MRT2.
Any chance Gadang getting 2 Viaduct packages?
Sosfinance, you are welcome. We should write more to benefit all member in I3investor .
2017-03-10 21:15
Not surprise Gadang can provide double digit growth with this RM952m project. Earnings will improve to above RM100m and rerating to PE 10-12x is not surprise.
(side track a bit, can also take a look at OCK-WA, I believe ripe for picking this year).
2017-03-10 22:15
sosfinance
@excelyou you did your homework. Good. That's what I said, Gadang has a good chance of getting ONE as 8 of the 11 winners of MRT1 has got their MRT2. Only, now 2 left for 3 viaducts. Since Muhibbah is out, Gadang submitted V205 AND V206. Thanks for highlighting on Muhibbah. Now we know, Gadang chances are even higher.
2017-03-03 16:34