TNB said it had received an addendum to the letter of award dated 3 Jun 2014 for Project 3B, which stated that the scheduled commercial operation dates for the two units of Project 3B should respectively be not later than 15 Jun 2019 and 15 Dec 2019. Project 3B was originally scheduled for commissioning in stages from 1 Oct 2018. The levelised tariff for Project 3B would be fixed at 26.67 sen/kWh as proposed jointly by TNB and Mitsui, 1.5 sen higher than when the project was first awarded to 1MDBMitsui early last year. TNB and Mitsui have seven days from 29 Jun 2015 to accept the terms of the addendum. (Source: Bursa Malaysia)
Comments: There are no major surprises and we remain positive on TNB in relation to the developments at Project 3B, given the ability of TNB and Mitsui to procure a higher levelised tariff to account for higher costs associated with project delays and forex fluctuation. We also note that the commercial operation dates have been pushed back, which is not surprising as the initial commercial operation dates were no longer realistic. As TNB-Mitsui would likely earn an appropriate internal rate of return on Project 3B with the proposed levelised tariff, we maintain our Buy rating on Tenaga with an unchanged TP of RM15.00.
Source: Affin Hwang Capital Research - 30 Jun 2015
Chart | Stock Name | Last | Change | Volume |
---|
2024-11-26
TENAGA2024-11-26
TENAGA2024-11-26
TENAGA2024-11-26
TENAGA2024-11-25
TENAGA2024-11-25
TENAGA2024-11-25
TENAGA2024-11-25
TENAGA2024-11-25
TENAGA2024-11-22
TENAGA2024-11-22
TENAGA2024-11-22
TENAGA2024-11-22
TENAGA2024-11-22
TENAGA2024-11-21
TENAGA2024-11-21
TENAGA2024-11-21
TENAGA2024-11-21
TENAGA2024-11-21
TENAGA2024-11-20
TENAGA2024-11-20
TENAGA2024-11-20
TENAGA2024-11-19
TENAGA2024-11-19
TENAGA2024-11-19
TENAGA2024-11-19
TENAGA2024-11-19
TENAGA2024-11-19
TENAGA2024-11-18
TENAGA2024-11-18
TENAGA2024-11-18
TENAGA2024-11-18
TENAGACreated by kltrader | Jan 03, 2023
Created by kltrader | Sep 30, 2022