you delay your completion date to Mar 2026 and yet you have announced your project to be completed on Mar 25 therefore you company share price will do correction to reflect this situation..
there is no fast route to success and you need to keep your word..
what angry....nanti bonus 2 bulan kasi gomen staf, 600 kasi pelajar SPM, 1300 bagi budak kolej and uni. baja free bagi felda settlers.....lagi menang besar....
First, at Oct-2023, said completed by March-2024. Then, at Jan 2024, said completed by June-2025. Now, at May-202, said completed by March-2026. Next, at Nov-2024, new date-line can be promised. Hahaha.
True, Ministers are not held accountable and can waffle through their teeth but WCE has made no comments on lateness except Section 7 b is being redesigned and no expected completion date.
As long as Sec 7 not completed. WCE will be like 2-expressway, one for Selangor, one for Perak. Traveler from Klang while reach Asam Jawa, got to back to old road. This will discourage traveler to take WCE to Taiping or Penang. Only festive period, traveler will take this alternative road.
As at end 04-24, Sec 7 reached 71%, base on progress of 1% per month, it take 29 months to complete, which is 09-26. Therefore, 06-26 still could not be finished.
Construction is not so straight forward, can't apportion by 1% or whatever amount per month Want to learn why, read the news in detail and you just might understand why