KLSE (MYR): GAMUDA (5398)
You're accessing 15 mins delay data. Turn on live stream now to enjoy real-time data!
Last Price
8.90
Today's Change
-0.13 (1.44%)
Day's Change
8.89 - 9.09
Trading Volume
6,341,400
2024-11-29
2024-11-29
2024-11-29
2024-11-29
2024-11-29
2024-11-29
2024-11-28
2024-11-28
2024-11-28
2024-11-28
2024-11-27
2024-11-27
2024-11-27
2024-11-27
2024-11-27
2024-11-26
2024-11-26
2024-11-26
2024-11-25
2024-11-25
2024-11-25
2024-11-23
2024-11-22
2024-11-22
2024-11-22
2024-11-22
2024-11-21
2024-11-21
2024-11-21
2024-11-20
2024-11-20
2024-11-20
2024-11-20
2024-11-19
2024-11-19
2024-11-19
2024-11-19
Victor Yong
8,271 posts
Posted by Victor Yong > 2018-10-09 11:29 | Report Abuse
later, mof will call for final meeting die to repeated begging, appeal, etc ... share price will rebound, fingers crossed :)
Reference is made to the Ministry of Finance’s (MoF) media statement dated Oct 7 in relation to the MRT 2 Project (project).
Save and except for the aforesaid MoF media statement, MMC-Gamuda has so far not received any communication nor notification from MRT Corp, the counter party to the award of the project. Thus, there has been no official confirmation from MRT Corp that MMC-Gamuda has been terminated as underground contractor.
Supportive of government’s drive to improve fiscal health
In spite of the agreed contract price, in view of the present austerity measures pursued by the new administration and in support, in particular of the new government’s review of its financial commitment on major infrastructure projects, MMC-Gamuda has been engaged in discussions and negotiations with MoF over the past two months to review the scope of works and specifications of the Project with the aim of reaching a compromise on cost reduction.
Following therefrom and at the request of MoF, MMC-Gamuda has agreed to convert the project delivery partner model to a single turnkey contract for the elevated works with a price reduction of 23%. In respect of the underground works, MMC-Gamuda has so far offered a 24% reduction for the balance of the underground works. Through its media statement, MoF has informed that it has accepted the offer in respect of the elevated and system works only.
Offered reduction for underground works
The underground works awarded contract price is RM15.47 billion. As progress achieved is now 40%, the balance of the uncompleted underground works is now valued at RM9.6 billion. MMC-Gamuda has offered a reduction of RM2.3 billion which represents 24% of this value. The reduction is achieved through reducing the scope of works and lowering specifications for mechanical, electrical and architectural finishes of the stations. It was also achieved by reducing the number of entrances to stations and the number of active stations constructed. From a total number of 10 stations, four will currently be shelved.
Factors influencing the awarded underground works price
There are two main factors that have a major influence on the price of the underground works, namely:
1) Employer’s requirements
In comparison with MRT Line 1, the employer’s requirements has increased the scope of works significantly, example: Larger floor space, a fivefold increase in the underground entrance and pedestrian walkways. As MRT Line 2’s geology is complex, the average depth of the diaphragm walls in MRT Line 2 is 51m as compared with MRT Line 1 at 39m. During the initial tender process, MMC-Gamuda had submitted an alternative proposal with savings by reducing the prescriptive requirements without compromising the safety, performance and functionality of the operational railway. However, MRT Corp elected not to accept the alternative offered by MMC-Gamuda. The reductions currently on offer to MoF include some of these alternatives but only those applicable to the balance of the underground works.
2) Safety requirements
Given the high risk of sinkhole incidents arising from tunnelling through the extreme karstic limestone in the city centre and threading the tunnels through high-end properties, with financial losses running into hundreds of millions if affected by ground collapses, the insurance industry around the world have introduced extremely stringent risk management requirements governed by International Tunnelling Insurance Group via the British Tunnelling Society Risk Management Code of Practice BS6164:2011 and ISO 31000 Risk Management.
Insurers have applied these measures on MRT Lines 1 and 2 tunnelling risks against which MRT Corp has in turn introduced strict pre-qualification requirements that cannot be relaxed for the insurance industry to insure MRT Corp on the project.
MMC-Gamuda’s continued in-house developments and customisation of the tunnel boring machines (TBM) is an integral part of managing this risk against sinkholes that proved successful in MRT Line 1. The Variable Density TBM was developed together with the German manufacturer and despite winning an international Innovation Award from British Tunnelling Society, it still needs ongoing improvements in its development to mitigate sinkhole risks more effectively.
The extent of the geological challenges presented in MRT Line 2 are reflected by the fact that of the 12 TBMs required, we need 10 TBMs to be of this variable density type to effectively mitigate the karstic risk. This also increases the quantum of enabling works of grouting and ground improvement prior to the tunnelling.