Most welcome secret1q, as we all could see from here that the reason of the price movement is lackluster as there is this ICPS here that causes the forward valuation of the share to be difficult and also a huge gap between min and max scenario even they secured a big project that is with PO valued at RM1.83bil a year. Please note that my earlier assuming is also considering they can fulfill the required amount of goods to be delivered which others already point out that it's a massive amount of sand, in fact.
HI guys, i want to do car porch tiling outside my nipah gate, however realize that the porch reaching to the road is slanting sideways, on the right is higher slope the way to the left front corner. The right cannot lower the ground else water cannot flow to the road. The left cannot make higher else it will be high hill slope for my car to drive in. If the car porch tiling do slope to the left front corner, the tiles might jack up at the one corner. My contractor also scratching head and propose to make the tile smaller. How to make it a smooth slope?
Guys! for Ageson we look into their project..........If want to see fundamental, go invest in Airasia, hahaha......And just a reminder Ageson free cash flow will be in good shape very soon, MARK MY WORDS!
1. is it more economical to build a house with concrete beam or steel beam? 2. how about the cost of building a basement/subterranean level. what factors need to be put into consideration. is it advisable to do so in malaysia, considering our climate, soil condition etc? 3. how about the wall building purposes, is it better to use red bricks, cement bricks or glass-wall? how about its thermal insulation property, as im considering passive cooling design for the house as to lower ac usage. 4. thinking of a 2/3 storey detached house with minimalist styling. thus its spacious and airy with lotsa light coming in, thus the question with the glass-wall... thanks for entertaining the questions...
1. depends. concrete beam is cheaper, but in some situation it's just not feasible to erect a concrete beam and a steel beam is a better option. 2. water table. and maybe soil condition. if both is preferable, then it makes much sense to build underground. 3. we're heavily designing (and implementing) passive cooling in our build. windcatcher, wind stack effect, directed airflow, insulated roof, natural ventilation. even considering AAC bricks. maybe you could take some pointers from our build.
1. how much more expensive is the steel beam compared to concrete beam? 2. 15 times more expensive than brickwall, eh? meaning, a 20m2 of window would costs 15 times more than an ordinary wall bricks, cements, paints etc. included? thinking of large windows actually, but used the term glass wall. yea, its aesthetics though... 3. and i assume the cost is after considering the insulated/low-e glass? or itll be more expensive with that option? 4. as for roofing material, would asphalt roofing be a good choice, considering our hot & rainy climate? worried about the possibility of the asphalt to melt down a bit under intense sunlight and to be compromised by sudden rain. ceramic seems to be tougher, but its also heavier. copper is an unorthodox choice, but might be prohibitively expensive. any opinions? 5. iinm, usually once the land has been cleared and the drainage built, itll be given some time to let the land settled. how long does this usually take? 6. whats a good practice for building cost estimates? excluding the land itself, how should the costs be broken down? 7. and what about the good practice in choosing the contractors to build the house? any advise?
still got 2-3 years maybe before doing anything with the house-building plan, or even longer, depending on the economic condition etc. meanwhile, i better prepare myself with necessary and relevant knowledge.
1. Steel is much more expensive than concrete per tonne, but if steel is used to reinforce concrete it is usually less than 1 percent by cross sectional area compared with the concrete. Even in concrete columns the steel is usually less than 4 percent. For steel construction using I beams and steel universal columns, the steel is a stronger material than concrete alone when of equal cross section, with good strength in both tension and compression, compared to the concrete which has only a fairly good strength in compression, with its limited strength in tension usually ignored for design purposes in reinforced concrete.. 2. prices for normal glass windows is around ~RM12 psft over here. including aluminium frame and installation. if i'm not mistaken. 3. cost for dual glazed, and tempered glass also depend on the frame quality. IINM it should be around RM50-70 psft depending on the thickness & type. 4. flat roofs constructed by concrete slabs will need asphalt treatment. not usually recommended for residential as it requires much more maintenance. 5. jkr spec need 1 year is the soil is new, not compacted. existing land after clearing usually don't need as long. 6. depending on area. and who you ask. 7. yeah. don't pick problematic ones. also higher priced doesn't mean better quality.
If I build a container house. Stack them up together with external roof do I need to apply any approval local government ? Kinda blur with the requirements
poundage is for temporary estimation / general checking only. engineer got their own structural design when come to this. (eg. the area of the steel and area of beam when come to section got certain ratio to comply therefore poundage is relate but is not 100% accurate) and also depend on the loading the poundage figure might deviated a lot.
bro, if i got no time for measurement, can use poundage? based on your experience, normally how much kg/m3 for floor beam for high rise building like condo? 200kg/m3?
200kg seems more than enough for beam. well, u can do sampling measurement. take a beam at ground floor and measure a beam. best is u have the accurate qty, because u have more qty, ur price no longer competitive, ur price less qty, u get the job and suffer loss.
so I understand ur position, possible request to get the rebar qty in contract is "provisional"?
I think i can answer this...........higher water table level will increase the temporary work. eg. when come to doing basement work fall below ground water level, then a lot of temporary work required as water will flood your working space while u executing ur piling work. even after piling work, it might penetrate through your cbp / diaphragm wall and hence increase the difficulty of ur work. though it is just water but it's a natural gravity of mother earth and will cause a big sum of money to execute that.
for tower crane, they use mobile crane to fix tower crane at bottom. then the tower crane will keep add the mast on itself to increase its height. can found those video on youtube in fact.
for backhoe, normal construction work don't need it at top level. but of course got exception got certain case. demolition of building usually need backhoe on the of building if it were to demolish 1 by 1. and yes, they use mobile crane to lift up the backhoe to the building. u will surprise that there were actually 500tonne mobile crane available for rent. daily rental could be abt RM50k a day.
I do agree with the investors which are caution on this share. The contract is too big for a company with no credibility. If the contract is worth billions, the current share price should reflect in it. Most likely the contract won't materialise and down (trade with caution).
The first two are only an MoU which is worrisome, but last one is PO. Even then PO could be canceled and we do not know the actual T&C of the PO and its impact to Ageson.
I guess that's why a lot of forum users here post up a lot of questions with a lot of uncertainty.
there are few method to bring down the crane. if the tower crane is not fix inside the boundary of building but outside attached to building, then the tower crane can dismantle itself. by taking out the mast 1 by 1 which subsequently lower down itself. until a certain low level, then will use the mobile crane to dismantle. below is the picture of tower crane that fix outside boundary of building.
for tower crane inside the building, there is not way to lower down. so usually the tower crane will hoist up a smaller crane and build it on top of building. that this second crane will proceed to dismantle tower crane and hoist it down. then to remove second crane, a even smaller crane would be hoisted up. same as the first crane, the third crane will dismantle the second crane and hoist it down. the third crane is generally smaller enough that can dismantle by pieces and carry through staircase / lift. below is picture of tower crane inside building boundary
This book is the result of the author's many years of experience and observation throughout his 26 years in the stockbroking industry. It was written for general public to learn to invest based on facts and not on fantasies or hearsay....
jeccy
235 posts
Posted by jeccy > 2020-05-08 13:30 | Report Abuse
Most welcome secret1q, as we all could see from here that the reason of the price movement is lackluster as there is this ICPS here that causes the forward valuation of the share to be difficult and also a huge gap between min and max scenario even they secured a big project that is with PO valued at RM1.83bil a year. Please note that my earlier assuming is also considering they can fulfill the required amount of goods to be delivered which others already point out that it's a massive amount of sand, in fact.