Posted by dragon328 > 2023-08-08 08:52 | Report Abuse
I could have missed this Sembcorp cogen plant. Being a cogen plant, part of the power output will be used to generate high pressure steam and demineralised water, so the net power output will be lower than 600MW, typically around 2/3 of nameplate capacity or around 400MW.
So now we have 2 firm new plants coming online in 2026 and another to be solicited by the EMA (not firm). If we factor in all three, total new capacity would be 600+400+600 = 1,600MW coming online by 2028. This would be just enough to meet the projected peak demand growth of 1,500MW - 3,800MW in next 5 years.